Microsoft starts second Westgate data centre in Auckland, with no public notification
HouGarden New Zealand, 25 November — Microsoft has begun building a second hyperscale data centre at Westgate in northwest Auckland, without a public announcement and without public notification by Auckland Council. Work started in September and is due to finish in 2028.
Then Prime Minister Jacinda Ardern announced Microsoft's plan to build hyperscale facilities in Auckland in 2020. The first Westgate data centre opened in December 2024. The second is going up directly in front of it, at 7 Kakano Rd, and is being built by Icon Construction.
The first centre's accounts give a guide to cost. Microsoft's accounts filed with the Companies Office for the year to June 30, 2025 show $800.2 million in direct capital expenditure on the first data centre. That included $246 million on the data centre and improvements, $197 million for capitalised borrowing costs and construction in progress, $286.4 million on servers and network equipment, $49.8 million for the land and $18.5 million for furniture and fittings. Total property, plant and equipment had a book value of $1.34 billion.
Microsoft Global Finance provided three loan facilities. They were $145 million at 2.31%, maturing on December 15, 2026; $200 million at 5.54%, repayable on demand; and $205 million at 5.96%, repayable on demand.
Consent documents give the second building a floor area of 10,879.8 sq m over two storeys. The first facility is 11,600 sq m. On that basis, the Herald's Tech Insider column estimates the second project could cost close to $1 billion. That is a reporter's estimate, not an official budget.
The second centre will be physically separate from the first. It will have its own power supply and backup, to help with failover and redundancy.
Microsoft has declined to confirm the location of its first data centre, citing a global security policy. Its address appears in consents, property records and marketing material from Westgate's developer. The company will say only that it already has a data "region" in Auckland. Amazon says the same, although it did not build on its own neighbouring Westgate site and took a $45 million impairment instead.
This time Microsoft has set up a "Microsoft in your community: Westgate datacentre project overview" website. It gives basic information on construction hours and footpath closures, and an email address for questions.
Microsoft did not answer questions about the finished project's physical dimensions, its capacity or noise mitigation. Data centre capacity is measured by peak power consumption in megawatts, and Microsoft has not disclosed it. A series of new subdivisions on Fred Taylor Drive, across the road, has been built since the first data centre gained consent.
A Microsoft spokesman said: "Construction has begun on the expansion of our New Zealand North Datacentre Region, which will support up to 500 jobs during peak construction and approximately 40 new permanent roles once operational." He added: "Access to local compute capacity is vital to the delivery of critical public services and to sustaining New Zealand's economy."
Not all the spending stays local. A Microsoft subsidiary in Ireland could buy hundreds of millions of dollars' worth of chips from Nvidia.
On cooling, the spokesman said: "The facility has been designed for New Zealand's unique climate, using air cooling to reduce energy use and eliminate water consumption for cooling." He added: "We're committed to developing our infrastructure responsibly and working closely with local communities as construction progresses." The data centre will not use evaporative cooling, and Microsoft says there will be "no chillers".
The council report is more detailed. It describes a mechanical chiller plant on the north side of the building, supported by closed-loop or air-cooled chillers rather than continuous open-loop water evaporation. The report notes that Microsoft's modern designs use closed-loop and outside-air cooling, needing minimal to zero water for continuous cooling.
The council's Senior Development Engineer assessed water and wastewater servicing. The water connection on Kakano Road is expected to be similar to other common industrial sites and not to place extreme demand on the public network. The cooling system is not expected to place abnormal demand on the public wastewater network. Groundwater would not be accessed. No maximum water use was prescribed.
Microsoft says its NZ North Cloud Region is supported by a 10-year agreement with Contact Energy for renewable power from Te Huka 3. Contact has said the Microsoft contract was a key reason it went ahead with the expansion. Te Huka 3 added 51 megawatts to the Te Huka geothermal station near Taupō and went online in December 2024.
When the Herald visited the site on Monday, a Vector employee said he was there to audit progress on a new substation to connect the data centre to the grid. He said Microsoft was paying for it. Vector has been approached for comment. Microsoft had no comment. Transpower said Vector was handling the project. The council report says Vector contractors will build the substation. It gives no megawatt capacity for the centre or the substation.
The report does detail large backup systems. There will be 13 diesel generators. Twelve main generators each have a 40,000-litre tank, and one smaller admin generator has an 8000-litre tank. That adds up to just under 500,000 litres of diesel on site. The generators are specified to compensate for up to 38MW of grid power. That is the grid supply they can replace, not a stated capacity for the data centre.
The council has been asked why the build was not publicly notified. Its report indicates notification was not required because the project is within scope for a light industrial area. Changes to the Resource Management Act came into force on October 6. They have left Aucklanders surprised by cell towers built outside their homes without notification. The second Microsoft data centre predates that change.
For nearby residents, the practical issues are construction noise and the new housing across the road. Microsoft has not said what noise measures it will use.
In 2020, after meetings and correspondence with Ardern, Microsoft gained Overseas Investment Office approval to buy 4ha of land at Westgate. The source article gives the address as 7 Kanano Rd, which appears to be a spelling error for Kakano Rd. Ardern, who first announced the investment, called it a vote of confidence in New Zealand's economy.
The application came from Microsoft 6399 New Zealand, a new vehicle owned by a Microsoft subsidiary in low-tax Ireland. The data centre business is still controlled by Microsoft Ireland Research. It made a $33.6 million profit on $215 million of revenue last year. It reported a tax benefit of $16.6 million after being in the red before the first data centre opened.
Microsoft Ireland Research also owns Microsoft's main local business, Microsoft New Zealand. It took control of that business in 2021 from a Bermuda-registered Microsoft subsidiary.
An anti-data centre protest movement has emerged in New Zealand. It mirrors campaigns in Australia, Europe and the United States, where data centres were a major issue in the midterm elections in states such as Ohio and Texas. The White House remains firmly behind large builds. Over the weekend President Donald Trump promised a "tremendous tax" penalty on any US company that built a data centre in another country. He gave no detail, and it is unclear whether it could be enacted without support from the newly blue Congress.
Other New Zealand projects have stalled. Microsoft's plan for a third site, at 151 Brigham Creek Rd near the Whenuapai airbase, 5km from Westgate, faltered. An Overseas Investment Office use-it-or-lose-it permission expired before Microsoft acquired the site. That may explain why the Westgate centres are called AKL02 and AKL03.
Amazon abandoned its large Westgate site next to Microsoft's after initial construction, and the site remains bare. It has chosen to co-locate with rivals for now.
Spark's planned "surf park" data centre at a new development in Dairy Flat, north of Auckland, was announced in 2023 and consented the following year. It remains on the drawing board. Spark sold 75% of its data centre business to Australian private equity firm Pacific Equity Partners earlier this year, and the pair formed a joint venture called TenPeaks.
Resource consent complications halted work on the wider Dairy Flat development, which includes housing, in May. The developer hopes to restart in February. TenPeaks would not comment while a resource consent review is under way, including on whether any preliminary work has been done on its data centre.
CDC, which is half owned by Infratil, and Contact Energy plan to team up on a 250MW data centre in Stratford, Taranaki. Infratil says the project is going through consents but has no timeline. For context, a recent Fitch survey said New Zealand's 60 data centres today have a combined capacity of 170MW.
Last month NextDC, Australia's largest listed data centre operator, pulled a consent application for a 15MW, five-storey data centre in the Auckland CBD. No reason was given. NextDC has lowered its spending in Australia and recently put the expansion of a Melbourne data centre on hold after intense community push-back.
In Southland, Datagrid has won key planning consents and negotiated a substation agreement with Transpower. It raised capital for initial earthworks by selling a 12.7% stake to Mercury Energy, a deal that implied a $417 million valuation. Datagrid has downsized its cable plans and is now aiming for a 280MW facility. Earthworks began in August, but founder Remi Galasso still needs venture capital and debt to pay for the data centre itself.
Icon's New Zealand director, Dan Bosher, declined to comment on the Westgate build. The source article suggests he may be bound by non-disclosure agreements. The project is a rare piece of good news for a construction sector that has been in a prolonged slump.